Garden Court Apartments - construction Update

WEEKLY UPDATE - December 5th, 2025

UNITS UNDER REPAIR:
Stacks 17, 15, 13, 11, 9, 7, 5, 3, and 1 are almost completed and in final punch stage.
Stacks 2 and 4 have concrete poured and are in completion stages
Stacks 6, 8, and 10 are scheduled to have concrete poured on 12/8

Demo is in progress for stacks 12, 14, 16, 18, 20, and 22

Miscellaneous:

Roman Piwko
Construction Manager
303-523-3733
Rpiwko@asrcompanies.com

Brian Gardner
Project Manager
720.827.2996