Quadrant Office Park

Repair and restoration of the 4-level parking structure for a commercial office building.

PROJECT INFORMATION

Duration:

3 Years

Value:

$2.35MM

Services Performed:

Concrete Repair & Waterproofing

Building & Structural Improvements

scope:

  • Pre-construction / construction management
  • Coordination of construction activities with tenants and property management team
  • Install and maintain multilevel stacked shoring
  • Inverted and double tee stem overhead repairs including installation of supplemental steel reinforcement and carbon fiber
  • Foundation and lite wall repairs
  • Corbel replacement with supplemental steel supports
  • Composite deck pan structural repairs
  • Replace connection plates at steel beam
  • Epoxy crack injection on structural members
  • Perform ground penetrating radar (GPR) or x-ray to locate existing rebar, conduit, etc. for installation of new drains
  • Partial/full depth repair of concrete deck; route and seal cracks; surface preparation of concrete substrate; application of traffic membrane system
  • Remove and replace joint and cove sealants

project outcomes:

  • Health and safety of tenants and the general public throughout active jobsite
  • Repair phasing critical to allow continuous site access and parking structure operation
  • Temporary enclosures and heat to perform work during winter conditions